Property manager · Bridgeport, Chicago
Rooftop plant replacement without closing the building
- Contract value
- $185,000
- Duration
- 6 weeks
The problem
Two end-of-life rooftop units serving a fully tenanted building, with no scope for a shutdown during business hours and a crane lift over an active street.
What we did
Phased overnight, one unit at a time, with temporary provision holding the occupied floors. Street closure permitted and cleared in a single weekend.
- Load calculation
- Crane lift
- Ductwork
- Controls
- Commissioning